Silver Creek Trail Extension to Lindale
Project ID:
2017 SPLOST
Project Type:
Capital Project
Project Status:
Approved
Status Updates
10.21.2025 - Norfolk Southern has verbally agreed to provide appraisal in 2025 on abandoned rail line from East 12th to Lindale. Multiple delays with project since 2019. The Rome-Floyd Land Bank has donated a parcel adjacent to the trail on E. 20th for a future trailhead.
9.23.2025 - Norfolk Southern merged with Union Pacific. Anticipate possible delays, but no indication at present.
1.30.2024 - No ETA on completion for official corridor appraisal. This project funding was split 50/50 with The City of Rome.
11.17.2023 - Norfolk Southern is finalizing surplus process and appraisals as of May 2023.