5th Avenue River District / Arts District
Project ID:
2017 SPLOST
Project Type:
Capital Project
Project Status:
Underway
Status Updates
10.21.2025 - Project broken into three phases. Utility work to go from aerial to underground has been underway and all conduit has been installed. The improvements along West 3rd in front of the NOVA project are complete and new pedestrian scale streetlights are being installed currently. Along 5th Avenue, pedestrian crosswalks and pedestrian signals have been installed.
4.14.2022 - GMC was engaged to do the project conceptual planning. Initial concepts were unveiled at a public input gathering session in September 2020. Pond & Company are working to complete the engineering and documents.