Airport Corporate Hangar Construction
Status Updates
10.21.2025 - Brooks Construction was awarded in March 2025. Nine (9) months to complete, including lead time for materials. Project is 25% complete.
5.13.2025 - the Floyd County Board of Commissioners approved Task Order No. 19 for Professional Services with CMT for $110,130.00.
2.25.2025 - the Floyd County Board of Commissioners approved award to Brooks Building Group, Inc for the construction of a Corporate Hangar for the Airport. This vendor provided the most responsive and responsible submission and submitted the lowest price submission.
4.23.2024 - the Floyd County Board of Commissioners approved Task Order No. 13 with CMT for the Corporate Hangar Project in the amount of $99,520.00.
11.17.2023 - Site selected and design underway. Construction in 2024.
3.2023 - Borings for potential sites with geologist. Site layout and design currently being evaluated for hangar construction.
1.24.2023 - the Floyd County Board of Commissioners approved RMG Task Order 5B - North Apron Expansion Design and Bidding Phase Services for a total of $89,590.00.