Floyd County Paving & Infrastructure
Project ID:
2023 SPLOST
Project Type:
Capital Project
Project Status:
Underway
Seventy-five (75) miles of repaving county maintained roadway.
| ORIGINAL PROJECT BUDGET | AMOUNT EXPENDED TO DATE | REMAINING FUNDS TO DATE | PROJECTED COMPLETION DATE |
|---|---|---|---|
| $10,600,000 | $519,136 | $10,080,864 | ONGOING |
Status Updates
7.16.2025 - Rubberized asphalt paving completed on Rush Chapel Rd. by NWGA Paving.
2.11.2025 - the Floyd County Board of Commissioners approved a grant with EPD to pave Rush Chapel Road with a Rubber Modified Asphalt (RMA). This will require a budget increase in Capital Projects for the total expense of $451,450. The County will have a match of $247,395 and this will be covered by the existing 2025 paving budget in 2023 SPLOST. This will require an increase to the Transfer from 2023 SPLOST in the amount of $247,395 and an increase to the Transfer to Capital Projects in the amount of $247,395.