Public Works Facilities Building

Project ID: 
2017 SPLOST
Project Type:
Capital Project
Project Status: 
Approved
Aerial of Public Works Camp (current)

Proposal for a new building for Public Works admin, main shop, warehouse, sign shop, landscape shop, facilities, bridge.

FINANCIALS - UPDATED 10.14.2025
ORIGINAL PROJECT ESTIMATE AMOUNTS EXPENDED TO DATE REMAINING FUNDS TO DATE PROJECTED COMPLETION
$2,450,000 $18,200 $2,431,800 TBD

 

Status Updates

10.14.2025 - Additional topo and site engineering scheduled for October with work to be completed by end of the month.

8.12.2025 - Floyd County Board of Commissioners approved a request from Public Works to add survey and civil design work to the existing architecture contract with Alan Bell for the Public Works Operation and Maintenance Building in the amount of $34,300.00. No change to the budget needed at this time.

11.17.2023 - Architect and plans are complete. Site selection is underway, and a potential site has been identified. Finalization of site in 2024.