Stadium Improvements
Status Updates
6.24.2025 - Field improvements are 100% complete and playable. We have had 24.32 inches of rain since season started and no issues.
4.22.2025 - the Floyd County Board of Commissioners approved a request from Facilities Management to approve a $219,705.00 increase to GL Account # 319639-66130-60066 for Advance Sports Group change order related to MLB required grading changes due to low tolerances of field elevation changes at AdventHealth Stadium.
4.8.2025 - Hitting tunnel 100% complete and in use. Field improvements 100% complete and playable.
4.8.2025 - the Floyd County Board of Commissioners approved change orders from Harbor Services for the renovation project at AdventHealth stadium in the amount of $12,870.00. This will require a budget increase in the amount of $12,870.00.
3.11.2025 - the Floyd County Board of Commissioners approved Change Orders for the Renovation Project at AdventHealth Stadium in the amount of $111,145.00. using 2017 SPLOST funds. These change orders have been submitted by Harbor Services, Inc. and have been discussed with The Sizemore Group, the architect of record for the project. This will require a budget increase in the amount of $111,145.00
3.11.2025 - the Floyd County Board of Commissioners approved a Change Order #3 from Advanced Sports Group for additional work on the Synthetic Turf at AdventHealth Stadium in the amount of $75,295.00 using 2017 SPLOST funds. This will be a budget increase.
2.25.2025 - the Floyd County Board of Commissioners approved change orders 17009 & 17010 from Harbor Services for the Rome Emperors Fieldhouse Renovation Project in the amount of $93,000.00.
2.11.2025 - the Floyd County Board of Commissioners approved:
- the purchase of netting for AdventHealth Stadium hitting tunnels from Sportsfield Specialties in the amount of $51,640.00 using funds from 2017 SPLOST. There is no change to the budget for 2025 needed.
- a change order from Advanced Sports Group to increase the water line size at the stadium and repair damaged fence along the outfield wall for a total of $34,020.00. This will require a change to the 2025 budget at this time.
1.28.2025 - the Floyd County Board of Commissioners approved a request from Purchasing to approve Change Order #17008 for the Renovation Project at AdventHealth Stadium in the amount of $52,940.00 using 2017 SPLOST funds. These change orders have been submitted by Harbor Services, Inc., the current contractor, for existing fire sprinkler system modifications.
1.15.2025 - the Floyd County Board of Commissioners approved a request from Purchasing to approve a contract pending final legal review with Advanced Sports Group for the purpose of replacing the AdventHealth Baseball Field with Synthetic Grass covering. This requires an increase to the 2017 SPLOST budget of $662,695.00
12.10.2024 - the Floyd County Board of Commissioners approved:
- a contract with Advanced Sports Group using Omnia Contract #R220504 for the turf replacement at AdventHealth Stadium using funds from 2017 SPLOST.
- a Change Order #17005 and #17006 from Harbor Services, Inc. for a total amount of $34,555.00.
10.22.2024 - the Floyd County Board of Commissioners approved awarding the purchase and installation of a batter's eye to Sportsfield Specialties in the amount of $156,880.00. This vendor submitted a responsive quote with the lowest pricing.
9.10.2024 - the Floyd County Board of Commissioners approved two (2) change orders for the renovation project for a total of $66,255.00. These change orders have been submitted by the current contractor, Harbor Services, Inc.
8.27.2024 - the Floyd County Board of Commissioners approved a request from Purchasing to award a bid to Sports Graphics - Field Wall Pads for AdventHealth Stadium in the amount of $101,455.00. This vendor submitted a responsive bid per our specifications and submitted the lowest bid. They will be able to complete the project in the timeframe set in the specifications.
8.13.2024 - the Floyd County Board of Commissioners approved a change order from Harbor Services construction contract for AdventHealth stadium in the amount of $45,155.00. This requires no change to the budget.
2.13.2024 - the Floyd County Board of Commissioners approved a request from Purchasing to approve the pricing proposal for the Rome Emperor Field House Renovation Project from Harbor Services, Inc. in the amount of $3,912,750.00 using 2017 SPLOST funds. This vendor is a partner with the Omnia Cooperative Agreement through the Lion Corp.
1.23.2024 - the Floyd County Board of Commissioners approved the Class C budget for the temporary locker rooms from BaAM in the amount of $653.985.00. This vendor was approved at the 12.12.2023 meeting.
3.2023 - Store expansion, Gate 6 covered canopy, and terrace enclosure completed. Projected completion of stadium improvements 2023-2024.
12.12.2023 - the Floyd County Board of Commissioners approved the use of professional services from BaAM for providing the design of temporary locker rooms in the amount of $22,800.00.
11.17.2023 - Additional PDL compliance under design for clubhouse. Expected completion 2024.