Texas Valley Infrastructure Expansion
Project ID:
2017 SPLOST
Project Type:
Capital Project
Project Status:
Approved
Status Updates
10.21.2025 - Project awarded to UWS Construction in November 2024.
42,860 linear feet of waterline has been installed. Services to residents currently being installed. Expect completion in late fall 2025.
11.17.2023 - Plans are complete and have been submitted to EPD for review. Plans are to bid in 2024. Project has been delayed due to 8-inch pipe supply in 2021-2022.